Operational Updates

Operation Update 26-01-2015

January 27th, 2015 by TRX Admin

PlantSideView

Completed Plant Structure

 

Operational Update 23-01-2015

January 23rd, 2015 by TRX Admin

SecondaryCrusherAssembly
Secondary Crusher
Pitmarking
Pit Markings
Pitentancearea
Pit Entrance
Crusherarea
Crusher Area

Operation update 20-01-2015

January 20th, 2015 by TRX Admin

FittingStaircaseclean

- Assembled FB26-28, FB26X, FB3, FB6, SB1-2, SS2, SP2, SB7
- Assembled FB49, FB52-53, FB55-57, FB49X, FB53X, 56X, SP1, SS3, RB3, RB2, RB1
- Erection (mission) now 85% complete.
- Lost 3hrs due to heavy rains
Viewshowingpositionedtanks

Tanks positioned and in place

FinishingMiddlecolumn

Middle section approaching completion

Technical Data
- All columns now erected
- All tanks now positioned
- Beams FB2X,FB11-FB-13, FB34-35, FB58-62 now installed
- Bracings HB9-11 now installed
- Stair case ss1-3 pre-assembled, and sp2 ladders

Operational Update Photos 14-01-2015

January 14th, 2015 by TRX Admin

a) 8x Columns in place

d) Side View

e) View Showing First Floor

High Grade Ore Material

December 23rd, 2014 by TRX Admin

Capture1

 

High Grade Material loaded on First Pad

 

Capture2

 

Ore Material on ROM Pad

 

Operational Update

December 3rd, 2014 by TRX Admin

Operational Update

December 3rd, 2014 by TRX Admin

Image Update – Buckreef

September 1st, 2014 by TRX Admin

DSC08375 DSC08387

DSC08363 DSC08410

DSC08366 DSC08396

An update with aerial views on the work done daily on bringing Buckreef Gold Company to production.

During the month of April 2014 the work and activities completed or ongoing for the heap leach
(HL) Pad construction being undertaken by Yale Constech Company

Click here to view Buckreef Gold Mine Development  Buckreef Gold Company Heap Leach Construction Works